HomeLocal GovernmentDepartments G - VPublic WorksProjects > 16th Avenue Bridge of Lions, 16th Avenue SE from 2nd Street to 4th Street, and 3rd Street SE east of 16th Avenue

Projects

16th Avenue Bridge of Lions, 16th Avenue SE from 2nd Street to 4th Street, and 3rd Street SE east of 16th Avenue

Bridge Rehabilitation, Pavement Reconstruction

SUBSCRIBE TO PROJECT NEWSLETTERS

Project Phase: Construction
Construction Start: April 2024


Construction Update: May 10, 2024

Road construction underway

16th Avenue/3rd Street SE Roadway Project

  • Work continues on 3rd Street SE from the 16th Avenue intersection to the Sinclair Basin area.
  • The service line to Tornadoes Grub and Pub has been transferred to the new main, which has been pressure tested and disinfected. 
  • The old pavement and sidewalk has been removed and the roadbed excavated to accommodate the proposed crushed rock base and new concrete pavement.
  • Storm sewer pipe and intake installation began on May 13, connecting to a recently installed storm sewer trunk line near Sinclair basin. It will extend to the intersection with 16th Avenue.
  • Storm sewer work is expected to take an additional 2 to 3 weeks, depending on weather conditions.

Road construction underway


16th Avenue Bridge over the Cedar River

  • Storm sewer work is expected to take two to three weeks, depending on weather conditions.

Past Updates


Key Contacts | 16th Avenue Bridge of Lions Maintenance Project

Contractor
Boulder Contracting, LLC
Luke Kjormoe
319-269-8680

City Construction Manager
Taylor Burgin
319-286-5524 | t.burgin@cedar-rapids.org

City Project Manager
AJ Barry, Snyder & Associates
319-362-9394  | ajbarry@snyder-associates.com

Key Contacts | 16th Avenue SE & 3rd Street Improvements

Contractor
Pirc-Tobin Construction, Incorporated
Mitch Ramler
563-590-9109

City Construction Manager
Taylor Burgin
319-286-5524 | t.burgin@cedar-rapids.org

City Project Manager
Lee Tippe
319-286-5816 | leet@cedar-rapids.org


Planned Improvements

16th Avenue Bridge of Lions Maintenance Project
Improvements will focus on deck repairs, joint replacements, and drainage and sidewalk modifications.

16th Avenue SE & 3rd Street Improvements
Improvements will transform the public right-of-way, with new sidewalks (including working with business to provide ADA accessible entrances where possible), storm sewer replacement in coordination with the Flood Control System, upgraded sanitary sewer, new driveways, undergrounding of utility cables, and new street lights. A separate, decorative streetscaping project is tentatively scheduled for construction in 2025.


Reference Materials:

© 2024  Cedar Rapids, Iowa, 101 First Street SE

Powered By Revize Login